Works ongoing
43
Sanctioned (pure scheme)
₹66.60 L
Expenditure since inception
₹30.11 L
Balance cost (unspent)
₹36.49 L
Wage ₹11.38 L · Material ₹25.11 L
Expenditure trend
−₹1.91 Cr
This Week
₹5.71 Cr
Last Week
▼ 133.5% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹1.20 Cr
Mandays trend
-1,47,030
This Week
-2,27,622
Last Week
▲ 35.4%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-88,895

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Works for Flood Control and Protection
2 works
₹15.15 L sanctioned
₹8.31 L spent (55%)
02
Constr of Cement Concrete Roads
1 works
₹14.91 L sanctioned
₹2.18 L spent (15%)
03
Construction of Trench
1 works
₹11.35 L sanctioned
₹3.16 L spent (28%)
04
Construction of Road and Culvert
1 works
₹11.06 L sanctioned
₹10.31 L spent (93%)
05
Rural Housing
30 works
₹7.05 L sanctioned
₹4.80 L spent (68%)
06
Plantation
2 works
₹4.12 L sanctioned
₹12,252 spent (3%)
07
Cattle Shed
3 works
₹2.29 L sanctioned
₹73,267 spent (32%)
08
Construction of Toilets
1 works
₹43,000 sanctioned
₹41,616 spent (97%)
09
Construction of NADEP/Vermi Compost Pit
2 works
₹24,568 sanctioned
₹7,040 spent (29%)
10
Boulder Check/Gully Plug
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 30 7.05 4.80 2.25
68%
2 Cattle Shed 3 2.29 0.73 1.56
32%
3 Plantation 2 4.12 0.12 4.00
3%
4 Works for Flood Control and Protection 2 15.15 8.31 6.84
55%
5 Construction of NADEP/Vermi Compost Pit 2 0.25 0.07 0.18
29%
6 Construction of Trench 1 11.35 3.16 8.19
28%
7 Constr of Cement Concrete Roads 1 14.91 2.18 12.73
15%
8 Construction of Toilets 1 0.43 0.42 0.01
97%
9 Construction of Road and Culvert 1 11.06 10.31 0.75
93%
Total 43 66.60 30.11 36.49