MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-23 10:44:59.16852
to
Reset filters
Works ongoing
28
Sanctioned (pure scheme)
₹39.99 L
Expenditure since inception
₹11.29 L
Balance cost (unspent)
₹28.70 L
Wage ₹16.95 L · Material ₹11.75 L
Expenditure trend
₹34.15 Cr
This Week
₹82.60 Cr
Last Week
▼ 58.7% vs last week
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
  • KATNI — BADWARA−₹27.11 L
Mandays trend
8,03,111
This Week
11,66,079
Last Week
▼ 31.1%
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
  • BETUL — GHORA DONGRI0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹19.69 L sanctioned
₹4.40 L spent (22%)
02
Plantation
4 works
₹11.72 L sanctioned
₹1.11 L spent (9%)
03
Rural Housing
10 works
₹2.70 L sanctioned
₹2.12 L spent (79%)
04
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.73 L spent (96%)
05
Construction of Crematorium
1 works
₹1.80 L sanctioned
₹1.77 L spent (98%)
06
Construction of NADEP/Vermi Compost Pit
9 works
₹1.78 L sanctioned
₹2,718 spent (2%)
07
Constr of Cement Concrete Roads
1 works
₹35,300 sanctioned
₹11,713 spent (33%)
08
Solid and Liquid Waste Management
1 works
₹15,000 sanctioned
₹1,158 spent (8%)
09
Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Goat Shelter
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 10 2.70 2.12 0.58
79%
2 Construction of NADEP/Vermi Compost Pit 9 1.78 0.03 1.75
2%
3 Plantation 4 11.72 1.11 10.61
10%
4 Solid and Liquid Waste Management 1 0.15 0.01 0.14
8%
5 Constr of Aganwadi 1 1.80 1.73 0.07
96%
6 Constr of Cement Concrete Roads 1 0.35 0.12 0.24
33%
7 Construction of Road and Culvert 1 19.69 4.40 15.29
22%
8 Construction of Crematorium 1 1.80 1.77 0.03
98%
Total 28 39.99 11.29 28.70
All 8 rows (zero-value rows hidden) ⇩ Export to Excel