Monitor — Ongoing Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works ongoing
16
Sanctioned (pure scheme)
₹21.37 L
Expenditure since inception
₹7.14 L
Balance cost (unspent)
₹14.22 L
Wage ₹9.06 L · Material ₹5.17 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
3 works
₹9.30 L sanctioned
₹93,024 spent (10%)
02
Well Recharge
1 works
₹4.96 L sanctioned
₹3.99 L spent (80%)
03
Farm Pond
2 works
₹4.75 L sanctioned
₹1.17 L spent (25%)
04
Rural Housing
10 works
₹2.35 L sanctioned
₹1.05 L spent (45%)
05
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)