Monitor — Ongoing Works
Rollup last refreshed: 2026-09-16 08:34:45.218851
Works ongoing
66
Sanctioned (pure scheme)
₹82.59 L
Expenditure since inception
₹40.26 L
Balance cost (unspent)
₹42.33 L
Wage ₹29.80 L · Material ₹12.53 L
Expenditure trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Mandays trend
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
17 works
₹40.93 L sanctioned
₹21.90 L spent (54%)
02
Construction of Well
8 works
₹17.22 L sanctioned
₹8.13 L spent (47%)
03
Rural Housing
34 works
₹7.99 L sanctioned
₹4.14 L spent (52%)
04
Construction of Percolation Tank
4 works
₹7.95 L sanctioned
₹261 spent (0%)
05
Construction of Bund
1 works
₹4.99 L sanctioned
₹4.15 L spent (83%)
06
Well Recharge
1 works
₹2.60 L sanctioned
₹1.94 L spent (74%)
07
Constr of Cement Concrete Roads
1 works
₹91,000 sanctioned
₹0 spent (0%)
08
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)
10
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)