Monitor — Ongoing Works

Rollup last refreshed: 2026-10-16 08:36:19.743515
to
Reset filters
Works ongoing
35
Sanctioned (pure scheme)
₹54.74 L
Expenditure since inception
₹20.27 L
Balance cost (unspent)
₹34.47 L
Wage ₹23.24 L · Material ₹11.23 L
Expenditure trend
−₹79.59 L
This Week
−₹78.03 L
Last Week
▼ 2% vs last week
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct
Mandays trend
-34,721
This Week
-33,130
Last Week
▼ 4.8%
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
28-Sep
12-Oct

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
5 works
₹16.03 L sanctioned
₹12.36 L spent (77%)
02
Grass Land Development
1 works
₹9.99 L sanctioned
₹141 spent (0%)
03
Plantation
3 works
₹6.87 L sanctioned
₹2.51 L spent (37%)
04
Construction of Well
2 works
₹4.88 L sanctioned
₹16,104 spent (3%)
05
Farm Pond
2 works
₹4.12 L sanctioned
₹2,272 spent (1%)
06
Construction of Tank
1 works
₹3.33 L sanctioned
₹380 spent (0%)
07
Rural Housing
13 works
₹3.05 L sanctioned
₹1.98 L spent (65%)
08
Construction of NADEP/Vermi Compost Pit
1 works
₹1.79 L sanctioned
₹270 spent (0%)
09
Constr of Cement Concrete Roads
2 works
₹1.59 L sanctioned
₹1.57 L spent (99%)
10
Construction of Bund
2 works
₹1.48 L sanctioned
₹12,480 spent (8%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 13 3.05 1.98 1.08
65%
2 Construction of Check Dam/Stop Dam 5 16.03 12.36 3.67
77%
3 Plantation 3 6.87 2.51 4.36
37%
4 Construction of Bund 2 1.48 0.12 1.35
8%
5 Construction of Well 2 4.88 0.16 4.71
3%
6 Farm Pond 2 4.12 0.02 4.10
1%
7 Constr of Cement Concrete Roads 2 1.59 1.57 0.02
99%
8 Construction of Crematorium 2 0.82 0.76 0.06
93%
9 Constr of Compound wall 1 0.79 0.78 0.01
98%
10 Grass Land Development 1 9.99 0.00 9.99
0%
11 Construction of NADEP/Vermi Compost Pit 1 1.79 0.00 1.79
0%
12 Construction of Tank 1 3.33 0.00 3.32
0%
Total 35 54.74 20.27 34.47
All 12 rows (zero-value rows hidden) ⇩ Export to Excel