Monitor — Ongoing Works
Rollup last refreshed: 2026-09-22 07:03:31.113676
Works ongoing
17
Sanctioned (pure scheme)
₹40.36 L
Expenditure since inception
₹11.57 L
Balance cost (unspent)
₹28.80 L
Wage ₹18.71 L · Material ₹10.09 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
- DEWAS — TONK KHURD−₹6,000
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹18.88 L sanctioned
₹24,012 spent (1%)
02
Construction of Well
2 works
₹14.29 L sanctioned
₹10.27 L spent (72%)
03
Plantation
3 works
₹4.23 L sanctioned
₹77,336 spent (18%)
04
Rural Housing
11 works
₹2.97 L sanctioned
₹28,854 spent (10%)
05
Constr of Food Grain storage
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)