Monitor — Ongoing Works
Rollup last refreshed: 2026-10-04 06:52:14.898992
Works ongoing
50
Sanctioned (pure scheme)
₹86.25 L
Expenditure since inception
₹1.72 L
Balance cost (unspent)
₹84.53 L
Wage ₹48.78 L · Material ₹35.75 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
9 works
₹37.22 L sanctioned
₹59,400 spent (2%)
02
Construction of Check Dam/Stop Dam
1 works
₹22.25 L sanctioned
₹54,000 spent (2%)
03
Construction of Well
6 works
₹17.69 L sanctioned
₹0 spent (0%)
04
Rural Housing
34 works
₹9.09 L sanctioned
₹58,800 spent (6%)
05
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
06
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)