MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
Reset filters
Works ongoing
23
Sanctioned (pure scheme)
₹72.48 L
Expenditure since inception
₹21.75 L
Balance cost (unspent)
₹50.73 L
Wage ₹26.88 L · Material ₹23.85 L
Expenditure trend
−₹1.31 Cr
This Week
−₹1.39 L
Last Week
▼ 9373.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • SHAHDOL — GOHPARU−₹38.03 L
Mandays trend
-34,842
This Week
-598
Last Week
▼ 5726.4%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹22.06 L sanctioned
₹12.53 L spent (57%)
02
Plantation
7 works
₹16.75 L sanctioned
₹84,525 spent (5%)
03
Construction of Well
3 works
₹10.51 L sanctioned
₹1.41 L spent (13%)
04
Construction of Trench
1 works
₹5.40 L sanctioned
₹62,543 spent (12%)
05
Constr of Gabion
1 works
₹4.74 L sanctioned
₹4.36 L spent (92%)
06
Construction of Tank
1 works
₹3.85 L sanctioned
₹663 spent (0%)
07
Farm Pond
1 works
₹3.39 L sanctioned
₹5,304 spent (2%)
08
Construction of Percolation Tank
1 works
₹3.38 L sanctioned
₹193 spent (0%)
09
Rural Housing
6 works
₹1.41 L sanctioned
₹1.04 L spent (74%)
10
Construction of Crematorium
1 works
₹99,000 sanctioned
₹87,868 spent (89%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Plantation 7 16.75 0.85 15.91
5%
2 Rural Housing 6 1.41 1.04 0.37
74%
3 Construction of Well 3 10.51 1.41 9.11
13%
4 Construction of Tank 1 3.85 0.01 3.85
0%
5 Construction of Crematorium 1 0.99 0.88 0.11
89%
6 Construction of Trench 1 5.40 0.63 4.77
12%
7 Farm Pond 1 3.39 0.05 3.34
2%
8 Constr of Gabion 1 4.74 4.36 0.38
92%
9 Construction of Percolation Tank 1 3.38 0.00 3.38
0%
10 Construction of Road and Culvert 1 22.06 12.53 9.53
57%
Total 23 72.48 21.75 50.73
All 10 rows (zero-value rows hidden) ⇩ Export to Excel