Monitor — Ongoing Works
Rollup last refreshed: 2026-10-05 07:04:05.423839
Works ongoing
34
Sanctioned (pure scheme)
₹53.54 L
Expenditure since inception
₹23.39 L
Balance cost (unspent)
₹30.16 L
Wage ₹15.35 L · Material ₹14.81 L
Expenditure trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
2 works
₹19.91 L sanctioned
₹10.84 L spent (54%)
02
Construction of Check Dam/Stop Dam
3 works
₹14.69 L sanctioned
₹1.80 L spent (12%)
03
Rural Housing
21 works
₹5.67 L sanctioned
₹3.71 L spent (65%)
04
Construction of Well
2 works
₹5.59 L sanctioned
₹5.32 L spent (95%)
05
Repair & Maint of Check Dam/Stop Dam
1 works
₹3.33 L sanctioned
₹94,830 spent (29%)
06
Plantation
1 works
₹2.02 L sanctioned
₹68,787 spent (34%)
07
Constr of Cement Concrete Roads
3 works
₹1.67 L sanctioned
₹7,080 spent (4%)
08
Repair & maint of Road
1 works
₹67,000 sanctioned
₹1,224 spent (2%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)