MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
Reset filters
Works ongoing
49
Sanctioned (pure scheme)
₹41.95 L
Expenditure since inception
₹25.21 L
Balance cost (unspent)
₹16.74 L
Wage ₹12.04 L · Material ₹4.70 L
Expenditure trend
−₹1.31 Cr
This Week
−₹1.39 L
Last Week
▼ 9373.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • SHAHDOL — GOHPARU−₹38.03 L
Mandays trend
-34,842
This Week
-598
Last Week
▼ 5726.4%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Solid and Liquid Waste Management
1 works
₹13.17 L sanctioned
₹13.06 L spent (99%)
02
Rural Housing
35 works
₹8.22 L sanctioned
₹4.58 L spent (56%)
03
Plantation
5 works
₹7.70 L sanctioned
₹2.00 L spent (26%)
04
Construction of Road and Culvert
1 works
₹4.65 L sanctioned
₹2.68 L spent (58%)
05
Farm Pond
2 works
₹2.95 L sanctioned
₹31,059 spent (11%)
06
Repair & Maint of Community infrastructure
1 works
₹2.24 L sanctioned
₹2.14 L spent (96%)
07
Construction of Bund
1 works
₹1.52 L sanctioned
₹28,803 spent (19%)
08
Culvert
1 works
₹88,000 sanctioned
₹486 spent (1%)
09
Constr of Cement Concrete Roads
1 works
₹57,000 sanctioned
₹9,396 spent (16%)
10
Construction of NADEP/Vermi Compost Pit
1 works
₹4,500 sanctioned
₹4,439 spent (99%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 35 8.22 4.58 3.64
56%
2 Plantation 5 7.70 2.00 5.70
26%
3 Farm Pond 2 2.95 0.31 2.64
11%
4 Construction of Road and Culvert 1 4.65 2.68 1.97
58%
5 Repair & Maint of Community infrastructure 1 2.24 2.14 0.10
96%
6 Construction of NADEP/Vermi Compost Pit 1 0.05 0.04 0.00
99%
7 Solid and Liquid Waste Management 1 13.17 13.06 0.11
99%
8 Culvert 1 0.88 0.00 0.88
1%
9 Constr of Cement Concrete Roads 1 0.57 0.09 0.48
17%
10 Construction of Bund 1 1.52 0.29 1.23
19%
Total 49 41.95 25.21 16.74