MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-21 07:05:18.038005
to
Reset filters
Works ongoing
13
Sanctioned (pure scheme)
₹54.88 L
Expenditure since inception
₹19.22 L
Balance cost (unspent)
₹35.66 L
Wage ₹11.44 L · Material ₹24.22 L
Expenditure trend
₹10.08 Cr
This Week
₹82.60 Cr
Last Week
▼ 87.8% vs last week
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
  • SAGAR — KESLI−₹2.89 L
Mandays trend
3,64,124
This Week
11,66,079
Last Week
▼ 68.8%
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
  • CHHATARPUR — CHHATARPUR-6

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹18.33 L sanctioned
₹13.01 L spent (71%)
02
Construction of Road and Culvert
1 works
₹17.90 L sanctioned
₹8,619 spent (0%)
03
Plantation
1 works
₹6.78 L sanctioned
₹2.52 L spent (37%)
04
Culvert
2 works
₹5.34 L sanctioned
₹2,652 spent (0%)
05
Constr of Cement Concrete Roads
3 works
₹2.83 L sanctioned
₹1.70 L spent (60%)
06
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.75 L spent (97%)
07
Solid and Liquid Waste Management
1 works
₹1.77 L sanctioned
₹1,326 spent (1%)
08
Constr of GP Bhawan
1 works
₹11,000 sanctioned
₹1,326 spent (12%)
09
Construction of NADEP/Vermi Compost Pit
1 works
₹2,000 sanctioned
₹204 spent (10%)
10
Construction of Toilets
1 works
₹0 sanctioned
₹10,320 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Constr of Cement Concrete Roads 3 2.83 1.70 1.13
60%
2 Culvert 2 5.34 0.03 5.31
1%
3 Construction of Check Dam/Stop Dam 1 18.33 13.01 5.32
71%
4 Constr of Aganwadi 1 1.80 1.75 0.05
97%
5 Constr of GP Bhawan 1 0.11 0.01 0.10
12%
6 Construction of NADEP/Vermi Compost Pit 1 0.02 0.00 0.02
10%
7 Construction of Road and Culvert 1 17.90 0.09 17.81
1%
8 Construction of Toilets 1 0.00 0.10 −0.10
0%
9 Plantation 1 6.78 2.52 4.26
37%
10 Solid and Liquid Waste Management 1 1.77 0.01 1.76
1%
Total 13 54.88 19.22 35.66
All 10 rows (zero-value rows hidden) ⇩ Export to Excel