MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-10-07 07:05:11.958669
to
Reset filters
Works ongoing
44
Sanctioned (pure scheme)
₹50.15 L
Expenditure since inception
₹22.46 L
Balance cost (unspent)
₹27.69 L
Wage ₹11.25 L · Material ₹16.44 L
Expenditure trend
₹11.52 Cr
This Week
₹27.93 Cr
Last Week
▼ 58.8% vs last week
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
  • SAGAR — SAGAR−₹82,664
Mandays trend
5,26,591
This Week
11,04,706
Last Week
▼ 52.3%
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
  • INDORE — SAWER0

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹14.84 L sanctioned
₹14.42 L spent (97%)
02
Construction of Check Dam/Stop Dam
1 works
₹14.58 L sanctioned
₹88,673 spent (6%)
03
Rural Housing
31 works
₹8.37 L sanctioned
₹3.55 L spent (42%)
04
Plantation
2 works
₹6.57 L sanctioned
₹2.45 L spent (37%)
05
Cattle Shed
2 works
₹2.04 L sanctioned
₹30,108 spent (15%)
06
Culvert
2 works
₹1.50 L sanctioned
₹17,894 spent (12%)
07
Constr of Cement Concrete Roads
2 works
₹1.03 L sanctioned
₹29,988 spent (29%)
08
Construction of Bund
1 works
₹55,847 sanctioned
₹5,967 spent (11%)
09
Solid and Liquid Waste Management
1 works
₹54,000 sanctioned
₹31,842 spent (59%)
10
Construction of Recharge Pits
1 works
₹12,000 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 31 8.37 3.55 4.82
42%
2 Plantation 2 6.57 2.45 4.13
37%
3 Constr of Cement Concrete Roads 2 1.03 0.30 0.73
29%
4 Cattle Shed 2 2.04 0.30 1.74
15%
5 Culvert 2 1.50 0.18 1.32
12%
6 Construction of Check Dam/Stop Dam 1 14.58 0.89 13.69
6%
7 Construction of Recharge Pits 1 0.12 0.00 0.12
0%
8 Solid and Liquid Waste Management 1 0.54 0.32 0.22
59%
9 Construction of Bund 1 0.56 0.06 0.50
11%
10 Construction of Road and Culvert 1 14.84 14.42 0.42
97%
Total 44 50.15 22.46 27.69
All 10 rows (zero-value rows hidden) ⇩ Export to Excel