Monitor — Ongoing Works
Rollup last refreshed: 2026-10-05 06:52:24.671994
Works ongoing
21
Sanctioned (pure scheme)
₹17.58 L
Expenditure since inception
₹25,800
Balance cost (unspent)
₹17.32 L
Wage ₹13.30 L · Material ₹4.02 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
2 works
₹9.02 L sanctioned
₹0 spent (0%)
02
Rural Housing
16 works
₹4.32 L sanctioned
₹25,800 spent (6%)
03
Construction of Spur
1 works
₹3.87 L sanctioned
₹0 spent (0%)
04
Constr of Cement Concrete Roads
1 works
₹25,000 sanctioned
₹0 spent (0%)
05
Construction of Toilets
1 works
₹12,000 sanctioned
₹0 spent (0%)
06
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)