MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
Reset filters
Works ongoing
157
Sanctioned (pure scheme)
₹85.61 L
Expenditure since inception
₹47.67 L
Balance cost (unspent)
₹37.94 L
Wage ₹23.07 L · Material ₹14.87 L
Expenditure trend
−₹1.31 Cr
This Week
−₹1.39 L
Last Week
▼ 9373.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Mandays trend
-34,842
This Week
-598
Last Week
▼ 5726.4%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
136 works
₹33.70 L sanctioned
₹20.07 L spent (60%)
02
Construction of Tank
1 works
₹14.67 L sanctioned
₹7.76 L spent (53%)
03
Roof Water Harvesting on gov/panchayat bldg
2 works
₹7.75 L sanctioned
₹2.86 L spent (37%)
04
Plantation
4 works
₹7.60 L sanctioned
₹4.45 L spent (59%)
05
Construction of Check Dam/Stop Dam
4 works
₹7.17 L sanctioned
₹2.72 L spent (38%)
06
Constr of Aganwadi
5 works
₹5.55 L sanctioned
₹4.11 L spent (74%)
07
Construction of Well
2 works
₹4.97 L sanctioned
₹2.33 L spent (47%)
08
Underground Dyke for Ground Water Recharge
1 works
₹2.97 L sanctioned
₹2.56 L spent (86%)
09
Constr of Cement Concrete Roads
1 works
₹76,000 sanctioned
₹72,954 spent (96%)
10
Constr of GP Bhawan
1 works
₹46,000 sanctioned
₹8,748 spent (19%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 136 33.70 20.07 13.64
60%
2 Constr of Aganwadi 5 5.55 4.11 1.44
74%
3 Construction of Check Dam/Stop Dam 4 7.17 2.72 4.45
38%
4 Plantation 4 7.60 4.45 3.15
59%
5 Construction of Well 2 4.97 2.33 2.64
47%
6 Roof Water Harvesting on gov/panchayat bldg 2 7.75 2.86 4.89
37%
7 Constr of GP Bhawan 1 0.46 0.09 0.37
19%
8 Construction of Tank 1 14.67 7.76 6.91
53%
9 Underground Dyke for Ground Water Recharge 1 2.97 2.56 0.41
86%
10 Constr of Cement Concrete Roads 1 0.76 0.73 0.03
96%
Total 157 85.61 47.67 37.94
All 10 rows (zero-value rows hidden) ⇩ Export to Excel