Monitor — Ongoing Works
Rollup last refreshed: 2026-10-24 08:28:45.135289
Works ongoing
44
Sanctioned (pure scheme)
₹1.08 Cr
Expenditure since inception
₹7.59 L
Balance cost (unspent)
₹1.01 Cr
Wage ₹59.54 L · Material ₹41.31 L
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹79.31 L sanctioned
₹94,482 spent (1%)
02
Rural Housing
35 works
₹9.45 L sanctioned
₹1.00 L spent (11%)
03
Construction of Well
3 works
₹8.43 L sanctioned
₹1.09 L spent (13%)
04
Construction of Percolation Tank
1 works
₹5.37 L sanctioned
₹42,339 spent (8%)
05
Construction of Trench
1 works
₹5.37 L sanctioned
₹4.13 L spent (77%)
06
Well Recharge
1 works
₹25,899 sanctioned
₹0 spent (0%)
07
Construction of Recharge Pits
1 works
₹25,177 sanctioned
₹261 spent (1%)
08
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)