Monitor — Ongoing Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
Reset filters
Works ongoing
48
Sanctioned (pure scheme)
₹32.06 L
Expenditure since inception
₹13.04 L
Balance cost (unspent)
₹19.02 L
Wage ₹16.30 L · Material ₹2.73 L
Expenditure trend
−₹20.03 L
This Week
−₹1.49 Cr
Last Week
▲ 86.6% vs last week
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹30.09 L
Mandays trend
-34,371
This Week
-94,475
Last Week
▲ 63.6%
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹10.32 L sanctioned
₹4.12 L spent (40%)
02
Rural Housing
34 works
₹7.99 L sanctioned
₹2.96 L spent (37%)
03
Construction of Well
2 works
₹4.65 L sanctioned
₹1.70 L spent (36%)
04
Boulder Check/Gully Plug
2 works
₹2.60 L sanctioned
₹8,063 spent (3%)
05
Culvert
1 works
₹2.11 L sanctioned
₹2.10 L spent (100%)
06
Solid and Liquid Waste Management
4 works
₹1.80 L sanctioned
₹1.57 L spent (87%)
07
Construction of Trench
1 works
₹1.32 L sanctioned
₹2,559 spent (2%)
08
Plantation
1 works
₹55,847 sanctioned
₹26,662 spent (48%)
09
Constr of Cement Concrete Roads
1 works
₹46,000 sanctioned
₹6,003 spent (13%)
10
Well Recharge
1 works
₹25,899 sanctioned
₹14,877 spent (57%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 34 7.99 2.96 5.02
37%
2 Solid and Liquid Waste Management 4 1.80 1.57 0.23
87%
3 Construction of Well 2 4.65 1.70 2.95
37%
4 Boulder Check/Gully Plug 2 2.60 0.08 2.52
3%
5 Well Recharge 1 0.26 0.15 0.11
57%
6 Constr of Cement Concrete Roads 1 0.46 0.06 0.40
13%
7 Construction of Check Dam/Stop Dam 1 10.32 4.12 6.20
40%
8 Construction of Trench 1 1.32 0.03 1.29
2%
9 Culvert 1 2.11 2.10 0.01
100%
10 Plantation 1 0.56 0.27 0.29
48%
Total 48 32.06 13.04 19.02
All 10 rows (zero-value rows hidden) ⇩ Export to Excel