Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 11:30:19.52397
to
Reset filters
Works ongoing
19
Sanctioned (pure scheme)
₹28.16 L
Expenditure since inception
₹5.18 L
Balance cost (unspent)
₹22.98 L
Wage ₹13.95 L · Material ₹9.04 L
Expenditure trend
₹10.08 Cr
This Week
₹39.19 Cr
Last Week
▼ 74.3% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • RAJGARH — SARANGPUR−₹1.02 Cr
Mandays trend
3,90,056
This Week
10,41,857
Last Week
▼ 62.6%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,443

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹6.42 L sanctioned
₹9,412 spent (1%)
02
Construction of Tank
1 works
₹6.13 L sanctioned
₹1.36 L spent (22%)
03
Construction of Well
1 works
₹4.45 L sanctioned
₹1.15 L spent (26%)
04
Boulder Check/Gully Plug
2 works
₹4.31 L sanctioned
₹99,588 spent (23%)
05
Constr of Cement Concrete Roads
1 works
₹2.00 L sanctioned
₹14,820 spent (7%)
06
Goat Shelter
3 works
₹1.91 L sanctioned
₹28,871 spent (15%)
07
Rural Housing
5 works
₹1.35 L sanctioned
₹59,556 spent (44%)
08
Well Recharge
4 works
₹1.04 L sanctioned
₹42,021 spent (41%)
09
Plantation
1 works
₹55,847 sanctioned
₹12,992 spent (23%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 5 1.35 0.60 0.75
44%
2 Well Recharge 4 1.04 0.42 0.62
41%
3 Goat Shelter 3 1.91 0.29 1.62
15%
4 Boulder Check/Gully Plug 2 4.31 1.00 3.32
23%
5 Construction of Tank 1 6.13 1.36 4.77
22%
6 Constr of Cement Concrete Roads 1 2.00 0.15 1.85
7%
7 Construction of Check Dam/Stop Dam 1 6.42 0.09 6.33
2%
8 Plantation 1 0.56 0.13 0.43
23%
9 Construction of Well 1 4.45 1.15 3.30
26%
Total 19 28.16 5.18 22.98
All 9 rows (zero-value rows hidden) ⇩ Export to Excel