Rollup last refreshed: 2026-10-02 06:51:56.129935
Works ongoing
50
Sanctioned (pure scheme)
₹38.72 L
Expenditure since inception
₹4.71 L
Balance cost (unspent)
₹34.01 L
Wage ₹21.24 L · Material ₹12.76 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
6 works
₹19.62 L sanctioned
₹0 spent (0%)
02
Rural Housing
39 works
₹10.53 L sanctioned
₹4.71 L spent (45%)
03
Construction of Well
3 works
₹4.70 L sanctioned
₹0 spent (0%)
04
Solid and Liquid Waste Management
1 works
₹3.50 L sanctioned
₹0 spent (0%)
05
Constr of Cement Concrete Roads
1 works
₹36,000 sanctioned
₹0 spent (0%)
06
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
07
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
10
Community Sanitary Complex
0 works
₹0 sanctioned
₹0 spent (0%)