Monitor — Ongoing Works
Rollup last refreshed: 2026-10-24 08:16:46.499239
Works ongoing
35
Sanctioned (pure scheme)
₹75.05 L
Expenditure since inception
₹3.32 L
Balance cost (unspent)
₹71.74 L
Wage ₹43.41 L · Material ₹28.32 L
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
3 works
₹21.50 L sanctioned
₹15,000 spent (1%)
02
Plantation
6 works
₹15.99 L sanctioned
₹35,400 spent (2%)
03
Construction of Well
5 works
₹10.73 L sanctioned
₹22,800 spent (2%)
04
Construction of Tank
1 works
₹10.00 L sanctioned
₹1.37 L spent (14%)
05
Repair & maint of Pond/ Tank
1 works
₹8.22 L sanctioned
₹0 spent (0%)
06
Rural Housing
16 works
₹4.32 L sanctioned
₹89,700 spent (21%)
07
Constr of Cement Concrete Roads
1 works
₹2.10 L sanctioned
₹0 spent (0%)
08
Solid and Liquid Waste Management
1 works
₹1.63 L sanctioned
₹0 spent (0%)
09
Farm Pond
1 works
₹55,865 sanctioned
₹31,200 spent (56%)