Monitor — Ongoing Works
Rollup last refreshed: 2026-09-07 07:03:15.513604
Works ongoing
18
Sanctioned (pure scheme)
₹42.24 L
Expenditure since inception
₹19.51 L
Balance cost (unspent)
₹22.73 L
Wage ₹8.12 L · Material ₹14.61 L
Expenditure trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
Mandays trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
6 works
₹16.51 L sanctioned
₹8.54 L spent (52%)
02
Construction of Road and Culvert
1 works
₹14.59 L sanctioned
₹7.81 L spent (54%)
03
Plantation
6 works
₹9.71 L sanctioned
₹3.17 L spent (33%)
04
Construction of Recharge Pits
3 works
₹85,713 sanctioned
₹0 spent (0%)
05
Well Recharge
2 works
₹57,142 sanctioned
₹0 spent (0%)
06
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Boulder Check/Gully Plug
0 works
₹0 sanctioned
₹0 spent (0%)