Monitor — Ongoing Works
Rollup last refreshed: 2026-10-06 07:04:43.876804
Works ongoing
23
Sanctioned (pure scheme)
₹42.61 L
Expenditure since inception
₹15.18 L
Balance cost (unspent)
₹27.42 L
Wage ₹11.51 L · Material ₹15.91 L
Expenditure trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
4 works
₹20.23 L sanctioned
₹4.14 L spent (20%)
02
Construction of Well
5 works
₹17.97 L sanctioned
₹8.45 L spent (47%)
03
Rural Housing
11 works
₹2.97 L sanctioned
₹1.89 L spent (64%)
04
Community Sanitary Complex
1 works
₹80,000 sanctioned
₹49,281 spent (62%)
05
Constr of Cement Concrete Roads
1 works
₹35,000 sanctioned
₹21,600 spent (62%)
06
Well Recharge
1 works
₹28,571 sanctioned
₹0 spent (0%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)