Monitor — Ongoing Works
Rollup last refreshed: 2026-10-07 07:05:11.958669
Works ongoing
9
Sanctioned (pure scheme)
₹30.96 L
Expenditure since inception
₹20.18 L
Balance cost (unspent)
₹10.79 L
Wage ₹4.16 L · Material ₹6.63 L
Expenditure trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
Mandays trend
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹17.27 L sanctioned
₹16.64 L spent (96%)
02
Plantation
2 works
₹5.33 L sanctioned
₹1.63 L spent (30%)
03
Repair & maint of Percolation Tank
1 works
₹4.71 L sanctioned
₹22,134 spent (5%)
04
Construction of Well
1 works
₹2.46 L sanctioned
₹1.04 L spent (42%)
05
Community Sanitary Complex
1 works
₹65,000 sanctioned
₹39,260 spent (60%)
06
Rural Housing
2 works
₹54,000 sanctioned
₹25,578 spent (47%)
07
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)