| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Rural Housing | 29 | 7.83 | 0.95 | 6.88 | 12% |
| 2 | Constr of Cement Concrete Roads | 3 | 1.60 | 0.00 | 1.60 | 0% |
| 3 | Constr of Aganwadi | 1 | 1.80 | 0.00 | 1.80 | 0% |
| 4 | Construction of Recharge Pits | 1 | 0.22 | 0.00 | 0.22 | 0% |
| Total | 34 | 11.45 | 0.95 | 10.50 |