| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Constr of Cement Concrete Roads | 2 | 1.21 | 0.00 | 1.21 | 0% |
| 2 | Farm Pond | 2 | 1.61 | 0.00 | 1.61 | 0% |
| 3 | Construction of Tank | 1 | 3.50 | 0.00 | 3.50 | 0% |
| 4 | Culvert | 1 | 0.20 | 0.00 | 0.20 | 0% |
| 5 | Plantation | 1 | 0.56 | 0.00 | 0.56 | 0% |
| 6 | Construction of Crematorium | 1 | 2.29 | 0.01 | 2.28 | 0% |
| Total | 8 | 9.37 | 0.01 | 9.36 |