Monitor — Ongoing Works
Rollup last refreshed: 2026-08-16 10:53:52.183387
Works ongoing
50
Sanctioned (pure scheme)
₹67.25 L
Expenditure since inception
₹26.33 L
Balance cost (unspent)
₹40.92 L
Wage ₹31.15 L · Material ₹9.77 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
1 works
₹24.50 L sanctioned
₹8.44 L spent (34%)
02
Constr of Cement Concrete Roads
1 works
₹15.69 L sanctioned
₹2.52 L spent (16%)
03
Rural Housing
43 works
₹10.10 L sanctioned
₹7.93 L spent (78%)
04
Plantation
2 works
₹8.54 L sanctioned
₹1.48 L spent (17%)
05
Construction of Crematorium
2 works
₹6.95 L sanctioned
₹5.67 L spent (82%)
06
Well Recharge
1 works
₹1.48 L sanctioned
₹29,261 spent (20%)
07
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Community Sanitary Complex
0 works
₹0 sanctioned
₹0 spent (0%)