Monitor — Ongoing Works
Rollup last refreshed: 2026-09-20 06:52:05.620266
Works ongoing
27
Sanctioned (pure scheme)
₹18.94 L
Expenditure since inception
₹27,300
Balance cost (unspent)
₹18.67 L
Wage ₹9.16 L · Material ₹9.51 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3 works
₹6.41 L sanctioned
₹0 spent (0%)
02
Rural Housing
17 works
₹4.59 L sanctioned
₹27,300 spent (6%)
03
Constr of Aganwadi
2 works
₹4.53 L sanctioned
₹0 spent (0%)
04
Construction of Crematorium
1 works
₹1.94 L sanctioned
₹0 spent (0%)
05
Constr of Cement Concrete Roads
2 works
₹84,000 sanctioned
₹0 spent (0%)
06
Plantation
1 works
₹55,847 sanctioned
₹0 spent (0%)
07
Construction of Percolation Tank
1 works
₹7,000 sanctioned
₹0 spent (0%)
08
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)