Monitor — Ongoing Works
Rollup last refreshed: 2026-08-06 11:29:13.728135
Works ongoing
36
Sanctioned (pure scheme)
₹1.01 Cr
Expenditure since inception
₹30.88 L
Balance cost (unspent)
₹69.93 L
Wage ₹32.62 L · Material ₹37.31 L
Expenditure trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
Slowest spending this week — worth a look
Mandays trend
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
22 works
₹46.88 L sanctioned
₹22.54 L spent (48%)
02
Construction of Tank
1 works
₹19.47 L sanctioned
₹1,044 spent (0%)
03
Construction of Check Dam/Stop Dam
2 works
₹12.04 L sanctioned
₹1.47 L spent (12%)
04
Construction of Well
5 works
₹10.60 L sanctioned
₹5.66 L spent (53%)
05
Solid and Liquid Waste Management
1 works
₹8.32 L sanctioned
₹9,709 spent (1%)
06
Farm Pond
1 works
₹1.85 L sanctioned
₹5,481 spent (3%)
07
Other Works
1 works
₹94,000 sanctioned
₹61,326 spent (65%)
08
Rural Housing
3 works
₹70,470 sanctioned
₹43,065 spent (61%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)