Monitor — Ongoing Works
Rollup last refreshed: 2026-09-21 07:03:55.111558
Works ongoing
36
Sanctioned (pure scheme)
₹51.34 L
Expenditure since inception
₹39.18 L
Balance cost (unspent)
₹12.16 L
Wage ₹4.17 L · Material ₹7.99 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
- DEWAS — TONK KHURD−₹6,000
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Cattle Shed
1 works
₹38.04 L sanctioned
₹31.38 L spent (82%)
02
Rural Housing
30 works
₹8.10 L sanctioned
₹5.91 L spent (73%)
03
Constr of Aganwadi
1 works
₹1.94 L sanctioned
₹1.36 L spent (70%)
04
Construction of Well
1 works
₹1.85 L sanctioned
₹48,250 spent (26%)
05
Construction of NADEP/Vermi Compost Pit
2 works
₹1.22 L sanctioned
₹2,298 spent (2%)
06
Construction of building/workshed for SHG
1 works
₹18,093 sanctioned
₹2,316 spent (13%)
07
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)