MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
Reset filters
Works ongoing
39
Sanctioned (pure scheme)
₹16.18 L
Expenditure since inception
₹7.07 L
Balance cost (unspent)
₹9.12 L
Wage ₹6.50 L · Material ₹2.62 L
Expenditure trend
−₹1.31 Cr
This Week
−₹1.39 L
Last Week
▼ 9373.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • SHAHDOL — GOHPARU−₹38.03 L
Mandays trend
-34,842
This Week
-598
Last Week
▼ 5726.4%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
24 works
₹5.64 L sanctioned
₹4.30 L spent (76%)
02
Construction of Play field
1 works
₹3.94 L sanctioned
₹29,640 spent (8%)
03
Construction of Embankment
1 works
₹2.21 L sanctioned
₹68,265 spent (31%)
04
Constr of Cement Concrete Roads
8 works
₹2.00 L sanctioned
₹1.36 L spent (68%)
05
Construction of Trench
1 works
₹1.36 L sanctioned
₹8,772 spent (6%)
06
Plantation
1 works
₹55,847 sanctioned
₹6,804 spent (12%)
07
Construction of NADEP/Vermi Compost Pit
1 works
₹24,860 sanctioned
₹3,480 spent (14%)
08
Solid and Liquid Waste Management
2 works
₹23,652 sanctioned
₹23,328 spent (99%)
09
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 24 5.64 4.30 1.34
76%
2 Constr of Cement Concrete Roads 8 2.00 1.36 0.64
68%
3 Solid and Liquid Waste Management 2 0.24 0.23 0.00
99%
4 Construction of Trench 1 1.36 0.09 1.27
6%
5 Plantation 1 0.56 0.07 0.49
12%
6 Construction of Embankment 1 2.21 0.68 1.53
31%
7 Construction of NADEP/Vermi Compost Pit 1 0.25 0.03 0.21
14%
8 Construction of Play field 1 3.94 0.30 3.64
8%
Total 39 16.18 7.07 9.12
All 8 rows (zero-value rows hidden) ⇩ Export to Excel