Monitor — Ongoing Works
Rollup last refreshed: 2026-10-26 10:02:28.474231
Works ongoing
30
Sanctioned (pure scheme)
₹27.50 L
Expenditure since inception
₹4.92 L
Balance cost (unspent)
₹22.58 L
Wage ₹14.86 L · Material ₹7.72 L
Expenditure trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
Mandays trend
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
- SINGRAULI — CHITRANGI-856
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
4 works
₹18.86 L sanctioned
₹76,854 spent (4%)
02
Rural Housing
25 works
₹6.71 L sanctioned
₹3.27 L spent (49%)
03
Constr of GP Bhawan
1 works
₹1.92 L sanctioned
₹87,886 spent (46%)
04
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Fish Drying Infrastructure
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Spur
0 works
₹0 sanctioned
₹0 spent (0%)