Monitor — Ongoing Works
Rollup last refreshed: 2026-09-21 07:03:55.111558
Works ongoing
49
Sanctioned (pure scheme)
₹21.76 L
Expenditure since inception
₹8.72 L
Balance cost (unspent)
₹13.04 L
Wage ₹9.53 L · Material ₹3.51 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
- DEWAS — TONK KHURD−₹6,000
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
45 works
₹12.15 L sanctioned
₹6.85 L spent (56%)
02
Construction of Check Dam/Stop Dam
1 works
₹4.56 L sanctioned
₹1.24 L spent (27%)
03
Construction of Tank
1 works
₹2.60 L sanctioned
₹41,228 spent (16%)
04
Plantation
2 works
₹2.45 L sanctioned
₹22,100 spent (9%)
05
Constr of Cement Concrete Roads
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)