Monitor — Ongoing Works

Rollup last refreshed: 2026-09-19 07:03:09.195652
to
Reset filters
Works ongoing
13
Sanctioned (pure scheme)
₹29.94 L
Expenditure since inception
₹4.51 L
Balance cost (unspent)
₹25.43 L
Wage ₹14.51 L · Material ₹10.92 L
Expenditure trend
₹28.67 Cr
This Week
₹39.19 Cr
Last Week
▼ 26.8% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • RAJGARH — SARANGPUR−₹1.04 Cr
Mandays trend
9,42,771
This Week
10,41,857
Last Week
▼ 9.5%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-16,417

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
1 works
₹6.49 L sanctioned
₹13,923 spent (2%)
02
Construction of Bund
1 works
₹6.17 L sanctioned
₹9,282 spent (2%)
03
Construction of Play field
1 works
₹4.47 L sanctioned
₹17,500 spent (4%)
04
Construction of Tank
1 works
₹3.85 L sanctioned
₹82,816 spent (21%)
05
Construction of Well
1 works
₹3.28 L sanctioned
₹51,692 spent (16%)
06
Construction of Crematorium
1 works
₹1.97 L sanctioned
₹11,580 spent (6%)
07
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.76 L spent (98%)
08
Rural Housing
5 works
₹1.35 L sanctioned
₹73,080 spent (54%)
09
Plantation
1 works
₹55,847 sanctioned
₹14,367 spent (26%)
10
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 5 1.35 0.73 0.62
54%
2 Construction of Play field 1 4.47 0.18 4.30
4%
3 Construction of Bund 1 6.17 0.09 6.08
2%
4 Constr of Aganwadi 1 1.80 1.76 0.04
98%
5 Plantation 1 0.56 0.14 0.41
26%
6 Construction of Tank 1 3.85 0.83 3.02
22%
7 Construction of Crematorium 1 1.97 0.12 1.85
6%
8 Construction of Well 1 3.28 0.52 2.76
16%
9 Construction of Percolation Tank 1 6.49 0.14 6.35
2%
Total 13 29.94 4.51 25.43
All 9 rows (zero-value rows hidden) ⇩ Export to Excel