Works ongoing
35
Sanctioned (pure scheme)
₹32.06 L
Expenditure since inception
₹27,900
Balance cost (unspent)
₹31.78 L
Wage ₹17.38 L · Material ₹14.40 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
- SHAJAPUR — MOMAN BADODIYA−₹26.22 L
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1 works
₹18.23 L sanctioned
₹0 spent (0%)
02
Rural Housing
26 works
₹7.02 L sanctioned
₹27,900 spent (4%)
03
Construction of Well
2 works
₹4.83 L sanctioned
₹0 spent (0%)
04
Solid and Liquid Waste Management
1 works
₹68,000 sanctioned
₹0 spent (0%)
05
Construction of Bund
1 works
₹38,000 sanctioned
₹0 spent (0%)
06
Constr of GP Bhawan
1 works
₹38,000 sanctioned
₹0 spent (0%)
07
Community Sanitary Complex
2 works
₹30,000 sanctioned
₹0 spent (0%)
08
Constr of Cement Concrete Roads
1 works
₹24,000 sanctioned
₹0 spent (0%)
09
Well Recharge
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)