Monitor — Ongoing Works

Rollup last refreshed: 2026-09-16 11:30:19.52397
to
Reset filters
Works ongoing
25
Sanctioned (pure scheme)
₹95.45 L
Expenditure since inception
₹65.18 L
Balance cost (unspent)
₹30.27 L
Wage ₹20.98 L · Material ₹9.29 L
Expenditure trend
₹10.08 Cr
This Week
₹39.19 Cr
Last Week
▼ 74.3% vs last week
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Slowest spending this week — worth a look
  • RAJGARH — SARANGPUR−₹1.02 Cr
Mandays trend
3,90,056
This Week
10,41,857
Last Week
▼ 62.6%
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,443

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹36.22 L sanctioned
₹33.83 L spent (93%)
02
Plantation
1 works
₹15.41 L sanctioned
₹3.38 L spent (22%)
03
Construction of Road and Culvert
1 works
₹11.44 L sanctioned
₹9.89 L spent (86%)
04
Construction of Well
4 works
₹10.80 L sanctioned
₹7.14 L spent (66%)
05
Constr of GP Bhawan
1 works
₹8.80 L sanctioned
₹6.96 L spent (79%)
06
Constr of Aganwadi
1 works
₹3.12 L sanctioned
₹4,224 spent (1%)
07
Construction of Bund
2 works
₹3.00 L sanctioned
₹58,752 spent (20%)
08
Rural Housing
8 works
₹2.09 L sanctioned
₹1.32 L spent (63%)
09
Construction of building/workshed for SHG
1 works
₹1.60 L sanctioned
₹92,804 spent (58%)
10
Constr of Compound wall
1 works
₹1.43 L sanctioned
₹44,004 spent (31%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 8 2.09 1.32 0.77
63%
2 Construction of Well 4 10.80 7.14 3.65
66%
3 Construction of Bund 2 3.00 0.59 2.41
20%
4 Construction of Tank 2 36.22 33.83 2.39
93%
5 Constr of Compound wall 1 1.43 0.44 0.99
31%
6 Plantation 1 15.41 3.38 12.03
22%
7 Constr of Aganwadi 1 3.12 0.04 3.08
1%
8 Constr of GP Bhawan 1 8.80 6.96 1.84
79%
9 Constr of Cement Concrete Roads 1 0.67 0.26 0.41
39%
10 Construction of Road and Culvert 1 11.44 9.89 1.54
87%
11 Construction of building/workshed for SHG 1 1.60 0.93 0.67
58%
12 Construction of Check Dam/Stop Dam 1 0.58 0.11 0.47
19%
13 Construction of Crematorium 1 0.30 0.30 0.00
99%
Total 25 95.45 65.18 30.27
All 13 rows (zero-value rows hidden) ⇩ Export to Excel