Rollup last refreshed: 2026-09-09 07:03:02.760628
Works ongoing
16
Sanctioned (pure scheme)
₹73.94 L
Expenditure since inception
₹54.98 L
Balance cost (unspent)
₹18.96 L
Wage ₹5.91 L · Material ₹13.05 L
Expenditure trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Slowest spending this week — worth a look
- SHAJAPUR — MOMAN BADODIYA−₹26.22 L
Mandays trend
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹32.54 L sanctioned
₹30.05 L spent (92%)
02
Construction of Bund
1 works
₹14.94 L sanctioned
₹13.42 L spent (90%)
03
Plantation
3 works
₹13.45 L sanctioned
₹3.70 L spent (28%)
04
Construction of Well
3 works
₹9.30 L sanctioned
₹4.95 L spent (53%)
05
Construction of Percolation Tank
1 works
₹2.00 L sanctioned
₹1.68 L spent (84%)
06
Rural Housing
6 works
₹1.71 L sanctioned
₹1.18 L spent (69%)
07
Constr of Kitchen Shed
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)