MGNREGA Works Dashboard
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
Reset filters
Works ongoing
73
Sanctioned (pure scheme)
₹32.30 L
Expenditure since inception
₹17.53 L
Balance cost (unspent)
₹14.76 L
Wage ₹10.71 L · Material ₹4.06 L
Expenditure trend
₹5.62 Cr
This Week
₹7.23 Cr
Last Week
▼ 22.3% vs last week
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Slowest spending this week — worth a look
  • SATNA — UNCHAHARA−₹70.09 L
Mandays trend
-63,750
This Week
-2,14,690
Last Week
▲ 70.3%
01-Jun
08-Jun
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-35,558

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
44 works
₹10.69 L sanctioned
₹5.55 L spent (52%)
02
Cattle Shed
8 works
₹8.48 L sanctioned
₹6.45 L spent (76%)
03
Construction of Tank
1 works
₹2.89 L sanctioned
₹2.63 L spent (91%)
04
Constr of Cement Concrete Roads
2 works
₹2.00 L sanctioned
₹2,100 spent (1%)
05
Farm Pond
1 works
₹2.00 L sanctioned
₹1.23 L spent (61%)
06
Construction of Percolation Tank
1 works
₹1.85 L sanctioned
₹21,555 spent (12%)
07
Construction of NADEP/Vermi Compost Pit
7 works
₹1.30 L sanctioned
₹34,183 spent (26%)
08
Construction of Recharge Pits
4 works
₹1.04 L sanctioned
₹19,700 spent (19%)
09
Culvert
1 works
₹88,000 sanctioned
₹79,555 spent (90%)
10
Construction of building/workshed for SHG
1 works
₹73,000 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 44 10.69 5.55 5.14
52%
2 Cattle Shed 8 8.48 6.45 2.03
76%
3 Construction of NADEP/Vermi Compost Pit 7 1.30 0.34 0.96
26%
4 Construction of Recharge Pits 4 1.04 0.20 0.84
19%
5 Solid and Liquid Waste Management 3 0.44 0.10 0.35
22%
6 Constr of Cement Concrete Roads 2 2.00 0.02 1.98
1%
7 Construction of Tank 1 2.89 2.63 0.26
91%
8 Culvert 1 0.88 0.80 0.08
90%
9 Construction of Percolation Tank 1 1.85 0.22 1.64
12%
10 Farm Pond 1 2.00 1.23 0.77
62%
11 Construction of building/workshed for SHG 1 0.73 0.00 0.73
0%
Total 73 32.30 17.53 14.76
All 11 rows (zero-value rows hidden) ⇩ Export to Excel