Monitor — Ongoing Works
Rollup last refreshed: 2026-10-12 07:04:13.185207
Works ongoing
11
Sanctioned (pure scheme)
₹11.04 L
Expenditure since inception
₹3.59 L
Balance cost (unspent)
₹7.45 L
Wage ₹3.03 L · Material ₹4.42 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
3 works
₹8.38 L sanctioned
₹1.59 L spent (19%)
02
Rural Housing
5 works
₹1.35 L sanctioned
₹97,380 spent (72%)
03
Community Sanitary Complex
3 works
₹1.31 L sanctioned
₹1.02 L spent (78%)
04
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
05
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
06
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Play field
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)