Monitor — Ongoing Works
Rollup last refreshed: 2026-09-06 07:04:10.165253
Works ongoing
75
Sanctioned (pure scheme)
₹50.48 L
Expenditure since inception
₹15.57 L
Balance cost (unspent)
₹34.91 L
Wage ₹22.66 L · Material ₹12.25 L
Expenditure trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
Mandays trend
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
2 works
₹23.74 L sanctioned
₹4.85 L spent (20%)
02
Rural Housing
71 works
₹19.17 L sanctioned
₹8.13 L spent (42%)
03
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹89,352 spent (18%)
04
Construction of Well
1 works
₹2.57 L sanctioned
₹1.70 L spent (66%)
05
Constr of Compound wall
0 works
₹0 sanctioned
₹0 spent (0%)
06
Constr of Gabion
0 works
₹0 sanctioned
₹0 spent (0%)
07
Constr of GP Bhawan
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of building/workshed for SHG
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Bund
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)