| Sr. | New Work Type | Ongoing works | Sanctioned | Expenditure | Balance cost | Exp. % |
|---|---|---|---|---|---|---|
| 1 | Construction of Check Dam/Stop Dam | 7 | 17.11 | 0.00 | 17.11 | 0% |
| 2 | Construction of Well | 2 | 4.46 | 0.00 | 4.46 | 0% |
| 3 | Construction of NADEP/Vermi Compost Pit | 2 | 0.28 | 0.00 | 0.28 | 0% |
| 4 | Construction of Percolation Tank | 1 | 14.09 | 0.00 | 14.09 | 0% |
| 5 | Construction of Tank | 1 | 3.38 | 0.00 | 3.38 | 0% |
| Total | 13 | 39.32 | 0.00 | 39.32 |