Monitor — Ongoing Works
Rollup last refreshed: 2026-10-04 06:52:14.898992
Works ongoing
5
Sanctioned (pure scheme)
₹26.18 L
Expenditure since inception
₹16,320
Balance cost (unspent)
₹26.02 L
Wage ₹22.06 L · Material ₹3.96 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Terracing
1 works
₹12.89 L sanctioned
₹0 spent (0%)
02
Construction of Trench
3 works
₹11.90 L sanctioned
₹16,320 spent (1%)
03
Farm Pond
1 works
₹1.39 L sanctioned
₹0 spent (0%)
04
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
05
Rural Housing
0 works
₹0 sanctioned
₹0 spent (0%)