Monitor — Ongoing Works

Rollup last refreshed: 2026-10-27 07:04:11.86929
to
Reset filters
Works ongoing
18
Sanctioned (pure scheme)
₹85.63 L
Expenditure since inception
₹46.96 L
Balance cost (unspent)
₹38.68 L
Wage ₹20.77 L · Material ₹17.90 L
Expenditure trend
−₹2.52 Cr
This Week
₹47.94 Cr
Last Week
▼ 105.3% vs last week
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Slowest spending this week — worth a look
  • SIDHI — SIHAWAL−₹1.81 Cr
Mandays trend
2,17,513
This Week
11,20,267
Last Week
▼ 80.6%
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
26-Oct
Lowest mandays this week — worth a look
  • SAGAR — BINA-12

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Repair & maint of Water Harvesting Structures
3 works
₹29.49 L sanctioned
₹24.84 L spent (84%)
02
Construction of Tank
1 works
₹24.41 L sanctioned
₹12.32 L spent (50%)
03
Construction of Trench
7 works
₹15.22 L sanctioned
₹6.83 L spent (45%)
04
Constr of Compound wall
1 works
₹9.24 L sanctioned
₹1.61 L spent (17%)
05
Farm Pond
2 works
₹3.67 L sanctioned
₹75,644 spent (21%)
06
Goat Shelter
1 works
₹1.33 L sanctioned
₹16,040 spent (12%)
07
Plantation
1 works
₹1.20 L sanctioned
₹15,400 spent (13%)
08
Construction of Bund
1 works
₹70,757 sanctioned
₹2,040 spent (3%)
09
Roof Water Harvesting on gov/panchayat bldg
1 works
₹36,698 sanctioned
₹26,250 spent (72%)
10
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Construction of Trench 7 15.22 6.83 8.39
45%
2 Repair & maint of Water Harvesting Structures 3 29.49 24.84 4.65
84%
3 Farm Pond 2 3.67 0.76 2.91
21%
4 Plantation 1 1.20 0.15 1.05
13%
5 Constr of Compound wall 1 9.24 1.61 7.62
18%
6 Construction of Bund 1 0.71 0.02 0.69
3%
7 Roof Water Harvesting on gov/panchayat bldg 1 0.37 0.26 0.10
72%
8 Construction of Tank 1 24.41 12.32 12.09
51%
9 Goat Shelter 1 1.33 0.16 1.17
12%
Total 18 85.63 46.96 38.68
All 9 rows (zero-value rows hidden) ⇩ Export to Excel