Monitor — Ongoing Works
Rollup last refreshed: 2026-10-01 06:51:54.859349
Works ongoing
13
Sanctioned (pure scheme)
₹51.86 L
Expenditure since inception
₹55,639
Balance cost (unspent)
₹51.30 L
Wage ₹21.11 L · Material ₹30.20 L
Expenditure trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Slowest spending this week — worth a look
Mandays trend
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
6 works
₹25.27 L sanctioned
₹0 spent (0%)
02
Constr of Aganwadi
1 works
₹14.83 L sanctioned
₹0 spent (0%)
03
Plantation
4 works
₹11.18 L sanctioned
₹41,135 spent (4%)
04
Rural Housing
2 works
₹57,000 sanctioned
₹14,504 spent (25%)
05
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)
06
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)
07
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)