MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
Reset filters
Works ongoing
27
Sanctioned (pure scheme)
₹49.90 L
Expenditure since inception
₹29.60 L
Balance cost (unspent)
₹20.30 L
Wage ₹3.53 L · Material ₹16.77 L
Expenditure trend
−₹20.03 L
This Week
−₹1.49 Cr
Last Week
▲ 86.6% vs last week
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹30.09 L
Mandays trend
-34,371
This Week
-94,475
Last Week
▲ 63.6%
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-17,779

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹14.99 L sanctioned
₹11.90 L spent (79%)
02
Construction of Other Community Building/Assets
1 works
₹11.68 L sanctioned
₹10.71 L spent (92%)
03
Construction of Well
2 works
₹6.26 L sanctioned
₹2.85 L spent (46%)
04
Cattle Shed
6 works
₹5.41 L sanctioned
₹25,600 spent (5%)
05
Construction of NADEP/Vermi Compost Pit
1 works
₹4.20 L sanctioned
₹26,350 spent (6%)
06
Rural Housing
14 works
₹3.45 L sanctioned
₹2.54 L spent (73%)
07
Construction of Recharge Pits
1 works
₹3.25 L sanctioned
₹45,840 spent (14%)
08
Constr of Cement Concrete Roads
1 works
₹65,000 sanctioned
₹62,046 spent (95%)
09
Construction of Spur
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 14 3.45 2.54 0.92
73%
2 Cattle Shed 6 5.41 0.26 5.15
5%
3 Construction of Well 2 6.26 2.85 3.41
46%
4 Construction of Other Community Building/Assets 1 11.68 10.71 0.97
92%
5 Constr of Cement Concrete Roads 1 0.65 0.62 0.03
96%
6 Construction of Recharge Pits 1 3.25 0.46 2.79
14%
7 Construction of Check Dam/Stop Dam 1 14.99 11.90 3.09
79%
8 Construction of NADEP/Vermi Compost Pit 1 4.20 0.26 3.94
6%
Total 27 49.90 29.60 20.30
All 8 rows (zero-value rows hidden) ⇩ Export to Excel