Monitor — Ongoing Works

Rollup last refreshed: 2026-10-06 07:04:43.876804
to
Reset filters
Works ongoing
26
Sanctioned (pure scheme)
₹51.86 L
Expenditure since inception
₹29.33 L
Balance cost (unspent)
₹22.53 L
Wage ₹4.36 L · Material ₹18.17 L
Expenditure trend
₹6.46 Cr
This Week
₹27.93 Cr
Last Week
▼ 76.9% vs last week
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Slowest spending this week — worth a look
  • SAGAR — SAGAR−₹82,664
Mandays trend
3,15,274
This Week
11,04,706
Last Week
▼ 71.5%
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
Lowest mandays this week — worth a look
  • CHHATARPUR — BIJAWAR-12

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
1 works
₹14.99 L sanctioned
₹11.90 L spent (79%)
02
Construction of Other Community Building/Assets
1 works
₹11.68 L sanctioned
₹10.71 L spent (92%)
03
Construction of Well
2 works
₹6.26 L sanctioned
₹2.85 L spent (46%)
04
Cattle Shed
6 works
₹5.41 L sanctioned
₹25,600 spent (5%)
05
Construction of NADEP/Vermi Compost Pit
1 works
₹4.20 L sanctioned
₹26,350 spent (6%)
06
Rural Housing
12 works
₹3.42 L sanctioned
₹2.19 L spent (64%)
07
Construction of Recharge Pits
1 works
₹3.25 L sanctioned
₹45,840 spent (14%)
08
Land Development
1 works
₹2.00 L sanctioned
₹7,987 spent (4%)
09
Constr of Cement Concrete Roads
1 works
₹65,000 sanctioned
₹62,046 spent (95%)
10
Construction of Tank
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 12 3.42 2.19 1.23
64%
2 Cattle Shed 6 5.41 0.26 5.15
5%
3 Construction of Well 2 6.26 2.85 3.41
46%
4 Construction of Check Dam/Stop Dam 1 14.99 11.90 3.09
79%
5 Land Development 1 2.00 0.08 1.92
4%
6 Construction of NADEP/Vermi Compost Pit 1 4.20 0.26 3.94
6%
7 Construction of Other Community Building/Assets 1 11.68 10.71 0.97
92%
8 Construction of Recharge Pits 1 3.25 0.46 2.79
14%
9 Constr of Cement Concrete Roads 1 0.65 0.62 0.03
96%
Total 26 51.86 29.33 22.53
All 9 rows (zero-value rows hidden) ⇩ Export to Excel