Monitor — Ongoing Works
Rollup last refreshed: 2026-10-24 08:28:45.135289
Works ongoing
13
Sanctioned (pure scheme)
₹28.17 L
Expenditure since inception
₹14.32 L
Balance cost (unspent)
₹13.85 L
Wage ₹2.85 L · Material ₹11.00 L
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Repair & Maint of Community infrastructure
1 works
₹14.99 L sanctioned
₹6.66 L spent (44%)
02
Plantation
5 works
₹7.50 L sanctioned
₹5.56 L spent (74%)
03
Construction of Well
1 works
₹2.51 L sanctioned
₹54,320 spent (22%)
04
Construction of NADEP/Vermi Compost Pit
2 works
₹1.45 L sanctioned
₹1.08 L spent (75%)
05
Community Sanitary Complex
1 works
₹86,000 sanctioned
₹20,413 spent (24%)
06
Rural Housing
3 works
₹85,500 sanctioned
₹27,246 spent (32%)
07
Construction of Check Dam/Stop Dam
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Other Community Building/Assets
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Percolation Tank
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Recharge Pits
0 works
₹0 sanctioned
₹0 spent (0%)