Monitor — Ongoing Works
Rollup last refreshed: 2026-09-21 07:03:55.111558
Works ongoing
19
Sanctioned (pure scheme)
₹63.87 L
Expenditure since inception
₹34.89 L
Balance cost (unspent)
₹28.98 L
Wage ₹7.34 L · Material ₹21.64 L
Expenditure trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Slowest spending this week — worth a look
- DEWAS — TONK KHURD−₹6,000
Mandays trend
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
7 works
₹20.43 L sanctioned
₹13.74 L spent (67%)
02
Plantation
6 works
₹16.34 L sanctioned
₹8.84 L spent (54%)
03
Construction of Tank
1 works
₹13.58 L sanctioned
₹6.67 L spent (49%)
04
Construction of Play field
1 works
₹6.38 L sanctioned
₹5.49 L spent (86%)
05
Constr of Gabion
2 works
₹4.88 L sanctioned
₹1,880 spent (0%)
06
Cattle Shed
2 works
₹2.26 L sanctioned
₹13,219 spent (6%)
07
Construction of NADEP/Vermi Compost Pit
0 works
₹0 sanctioned
₹0 spent (0%)
08
Construction of Road and Culvert
0 works
₹0 sanctioned
₹0 spent (0%)
09
Construction of Toilets
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
0 works
₹0 sanctioned
₹0 spent (0%)