Works ongoing
57
Sanctioned (pure scheme)
₹35.82 L
Expenditure since inception
₹19,800
Balance cost (unspent)
₹35.63 L
Wage ₹17.81 L · Material ₹17.81 L
Expenditure trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Slowest spending this week — worth a look
Mandays trend
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
07-Sep
14-Sep
21-Sep
28-Sep
05-Oct
12-Oct
19-Oct
Lowest mandays this week — worth a look
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹19.75 L sanctioned
₹0 spent (0%)
02
Rural Housing
51 works
₹12.78 L sanctioned
₹19,800 spent (2%)
03
Constr of Cement Concrete Roads
3 works
₹2.58 L sanctioned
₹0 spent (0%)
04
Construction of Play field
1 works
₹72,000 sanctioned
₹0 spent (0%)
05
Construction of Crematorium
0 works
₹0 sanctioned
₹0 spent (0%)
06
Farm Pond
0 works
₹0 sanctioned
₹0 spent (0%)