MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Monitor — Ongoing Works

Rollup last refreshed: 2026-09-05 15:48:06.554457
to
Reset filters
Works ongoing
70
Sanctioned (pure scheme)
₹72.22 L
Expenditure since inception
₹30.07 L
Balance cost (unspent)
₹42.15 L
Wage ₹35.00 L · Material ₹7.15 L
Expenditure trend
₹26.97 Cr
This Week
₹28.12 Cr
Last Week
▼ 4.1% vs last week
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Slowest spending this week — worth a look
  • DHAR — TIRLA−₹33.18 L
Mandays trend
11,02,650
This Week
9,10,292
Last Week
▲ 21.1%
15-Jun
22-Jun
29-Jun
06-Jul
13-Jul
20-Jul
27-Jul
03-Aug
10-Aug
17-Aug
24-Aug
31-Aug
Lowest mandays this week — worth a look
  • DHAR — KUKSHI-16,901

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
7 works
₹21.65 L sanctioned
₹88,538 spent (4%)
02
Construction of Check Dam/Stop Dam
1 works
₹14.97 L sanctioned
₹13.20 L spent (88%)
03
Rural Housing
54 works
₹14.58 L sanctioned
₹5.64 L spent (39%)
04
Construction of Road and Culvert
1 works
₹14.36 L sanctioned
₹9.98 L spent (70%)
05
Plantation
2 works
₹4.85 L sanctioned
₹22,332 spent (5%)
06
Constr of Cement Concrete Roads
3 works
₹1.11 L sanctioned
₹6,188 spent (6%)
07
Solid and Liquid Waste Management
1 works
₹55,046 sanctioned
₹1,989 spent (4%)
08
Construction of Recharge Pits
1 works
₹14,467 sanctioned
₹5,018 spent (35%)
09
Construction of Trench
0 works
₹0 sanctioned
₹0 spent (0%)
10
Construction of Well
0 works
₹0 sanctioned
₹0 spent (0%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Ongoing works Sanctioned Expenditure Balance cost Exp. %
1 Rural Housing 54 14.58 5.64 8.94
39%
2 Farm Pond 7 21.65 0.89 20.77
4%
3 Constr of Cement Concrete Roads 3 1.11 0.06 1.05
6%
4 Plantation 2 4.85 0.22 4.63
5%
5 Construction of Check Dam/Stop Dam 1 14.97 13.20 1.77
88%
6 Construction of Road and Culvert 1 14.36 9.98 4.38
70%
7 Solid and Liquid Waste Management 1 0.55 0.02 0.53
4%
8 Construction of Recharge Pits 1 0.14 0.05 0.09
35%
Total 70 72.22 30.07 42.15