Data as of 29 Oct 2026, 06:52 Admin login
FY
Reset

Dashboard for works

Every work in the selected area, by status, with what was sanctioned and spent. Expenditure % counts ongoing works only.

VBGRAMG
17.5%
COMPLETED
17.5% completed
incl. physically completed · inner ring
0.2% spent on ongoing works
₹9,600 of ₹38.90 L · outer ring
42.5% ongoing
17 works
Total works
40
Sanctioned₹44.68 L
Expenditure₹23,700
Spent on ongoing works0.2%
Approved
14
35.0% of all works
Sanctioned₹3.99 L
Expenditure₹0
Completed
7
17.5% of all works
Sanctioned₹1.78 L
Expenditure₹14,100
New
2
5.0% of all works
Sanctioned₹0
Expenditure₹0
Ongoing
17
42.5% of all works
Sanctioned₹38.90 L
Expenditure₹9,600
Breakdown

By block