Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
32 works
₹1.94 Cr sanctioned
₹1.86 Cr spent (96%)
02
Construction of Check Dam/Stop Dam
14 works
₹1.58 Cr sanctioned
₹1.46 Cr spent (93%)
03
Works for Flood Control and Protection
10 works
₹1.42 Cr sanctioned
₹1.33 Cr spent (94%)
04
Construction of Percolation Tank
10 works
₹1.08 Cr sanctioned
₹97.86 L spent (91%)
05
Construction of Tank
5 works
₹66.68 L sanctioned
₹60.78 L spent (91%)
06
Construction of Bund
5 works
₹66.02 L sanctioned
₹62.11 L spent (94%)
07
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
4 works
₹56.81 L sanctioned
₹53.36 L spent (94%)
08
Construction of Trench
3 works
₹20.16 L sanctioned
₹16.65 L spent (83%)
09
Land Development
2 works
₹19.41 L sanctioned
₹17.46 L spent (90%)
10
Constr of GP Bhawan
1 works
₹14.48 L sanctioned
₹9.40 L spent (65%)